On this page you will find the steps to connect the ABB DC Charger to the E-Flux by Road platform.

Jochem Boot avatar
Written by Jochem Boot
Updated over 9 months ago

Configuration Requirements

  • Configuration package E-Flux by Road

    • Contains: EVSE ID, configuration manual for the installer and registration manual for the owner of the charging station

  • Online manual ABB DC charger

Follow the steps:

Step 1: Get in touch with your contact at ABB.


Step 2: Ask him/her if the charging station can be set to E-Flux. Provide the following URL ws://ocpp.e-flux.nl/1.6/e-flux and your serial number.


Step 3: Once you receive confirmation that the charging station was set to E-Flux continue with the next steps.

If you are the installer of the charging station, go to step 4. If you are the owner of the charging station, go to step 5.

Step 4: Complete the following steps to activate the station on the E-Flux by Road platform:

  1. Login to your Field Service Account or create a Field Service Account via www.e-flux.io/installer-signup*.

  2. Go to “Setup New EVSE” in the menu on the left and enter the serial number or OCPP ID of the station.

  3. Click on “Setup charging station”.

  4. Click on Upload Configuration, then click Next.

  5. Choose and define the connector type, and choose “Save Connector Configuration”.

  6. The charging station is now activated and ready to be registered by the owner!

*A Field Service Account is for installers only and will be used as a point of contact for technical tickets.

Step 5: Complete the following steps to register the station on the E-Flux by Road platform:

  1. Ask your installer to complete Step 3 to finish the configuration of your charger, or call E-Flux by Road to finish the configuration.

  2. Create an E-Flux by Road account by going to www.e-flux.io/signup.

    • Is this charging station facilitated by your employer? Check your email for the invitation.

  3. Follow the steps to add the location and register your charging station.

  4. Put the sticker with the QR code on the charging station so it’s easier to identify the station if you need support.

  5. The charging station is now registered and ready to be used!

The charging station is now connected to the E-Flux by Road platform!