Manual: Vestel ECV10
Manual: Vestel ECV10
Gina ter Heide avatar
Written by Gina ter Heide
Updated over 2 months ago

Configuration Requirements

  • Configuration package E-Flux by Road

    • Contains: Sim card (optional), EVSE ID, configuration manual for the installer and registration manual for the owner of the charging station

  • Laptop.

  • UTP cable

Follow the steps

If you want to connect the charging station’s WEB configuration interface, you have two options;

Step 1/1: You can directly connect your PC to the charging station using a Ethernet cable. If you follow this option, please make sure that you have properly configured your charging station’s LAN interface to static IP.

Step 1/2: You can use a router having DHCP server. In this option, both the charging station and the PC should be connected to the router. Please be sure that you need to check the IP adress from the router to be able to make the connection. They should both get a IP adres in the same range.

For direct PC connection option, you need to connect your PC to the charging station to set up the ocpp configuration.

Step 2: Open your WEB browser and type 192.168.0.10 which is IP address of the web interface.

Step 3: You will see the login page on your browser; When it's the first time of entering the WEB Config interface or if you never changed your password yet, you will see the warning which is “We recommend you to change your default password from system maintenance menu”.

You can enter the system with:

Default username = admin

Default password = admin

You can change password with Change Password Button in login page or Administration Password section in the System Maintenance tab.

Attention: For WEB configuration interface accessibility problems; WEB browsers usually save some information from Websites in its cache and cookies. Forcing Refresh or Clearing (depending on your operating system and browser) them fixes certain problems, like loading or formatting issues on WEB page

Step 4: If you select mode as "Enabled"; you should type all fields in the connection settings and configuration parameters sections are enable. For now, the only available OCPP version is OCPP 1.6, so it will be selected as default.

The Central System Address and Charge Point Id are mandatory fields for saving this page.

So it needs to be set up like this:

Ocpp Connection: Enabled

Ocpp Version: 1.6 / 1.6 Json

Connection Settings

Central system address: ws://ocpp.e-flux.nl/1.6/e-flux

Charge point id: ‘'Serial number of the charger’'

Then, click on the "Save" button.

Please be careful for your entered values because the system does not accept the unsuitable values and gives the warning.

Step 5: Complete the following steps to activate the station on the E-Flux by Road platform:

  1. Login to your Field Service Account or create a Field Service Account via www.e-flux.io/installer-signup*.

  2. Go to “Setup New EVSE” in the menu on the left and enter the serial number or OCPP ID of the station.

  3. Click on “Setup charging station”.

  4. Click on Upload Configuration, then click Next.

  5. Choose and define the connector type, and choose “Save Connector Configuration”.

  6. The charging station is now activated and ready to be registered by the owner!

*A Field Service Account is for installers only and will be used as a point of contact for technical tickets.

Step 6: Complete the following steps to register the station on the E-Flux by Road platform:

  1. Ask your installer to complete Step 9 to finish the configuration of your charger, or call E-Flux by Road to finish the configuration.

  2. Create an E-Flux by Road account by going to www.e-flux.io/signup.

    • Is this charging station facilitated by your employer? Check your email for the invitation.

  3. Follow the steps to add the location and register your charging station.

  4. Put the sticker with the QR code on the charging station so it’s easier to identify the station if you need support.

  5. The charging station is now registered and ready to be used!

The charging station is now connected to the E-Flux by Road platform